Subdivisions & NBN Pathways
At M-Electrics, we specialise in electrical services for land subdivisions across Western Australia. We handle everything from the installation of site main switchboards to underground conduit provisions to meet all requirements set by Western Power and WAPC, ensuring a seamless and hassle-free process when subdividing land.
Why M-Electrics
- Expertise: Decades of experience in the Western Australian electrical industry.
- Compliance and Safety: Adherence to all Western Power and Western Australian Planning Commission (WAPC) regulations.
- End-to-End Solutions: From planning and installation to final connections and applications.
- Customer-Focused: Reliable communication and transparent pricing with no surprises.
Our Subdivision Services
- Main Switchboard Installation: Professional setup and installation of site main switchboards for new survey strata developments.
- Underground Conduit Provisions: Compliant and efficient underground electrical infrastructure to meet Western Australian Planning Commission (WAPC) and Western Power requirements.
- Overhead to Underground Power Conversions: When subdividing land existing houses must be changed to underground power.
- NBN and Western Power Applications: Preparation and submission of all required applications, taking the stress out of dealing with utility providers.
FAQs
Tap a question to reveal the answer.
-
The existing house has an overhead service. Does this need to be changed to underground? (click to expand)Yes, the overhead service must be removed, and the existing connection converted to an underground service.
-
Where will the Site Main Switchboard be located? (click to expand)
The SMSB must be positioned within 30 meters of the Western Power dome and placed on common property or within an easement.
-
Subdivisions around me don’t seem to have a Site Main Switchboard. Why is that? (click to expand)
Prior to 2020, it was permitted to have two connections into a Western Power dome. This is no longer allowed. Additionally, those subdivisions may be green-titled lots, which follow different regulations.
-
I have an existing green dome. Do I still need to apply to Western Power? (click to expand)Yes, an application is required. Western Power needs to allocate additional supply capacity for the newly subdivided lots.
-
Do I need to pay Western Power for the installation or use of an existing Green Dome? (click to expand)
Yes, Western Power requires payment of headworks fees for the installation or use of an existing Green Dome.
-
Can M-Electrics assist me with the Western Power application? (click to expand)
Yes! We will handle the entire process, including preparation, submission, and liaison with Western Power—you won’t need to lift a finger.
-
What are Underground Conduit Provisions? (click to expand)
We generally install conduits only. Once the subdivided lots commence construction, the builder will extend the provisions to the final location on the new building and pull the cable to the SMSB.
-
Can M-Electrics assist me with the NBN application? (click to expand)
Yes! We will handle the entire process, including preparation, submission, and liaison with NBN —you won’t need to lift a finger.
-
How long does it take Western Power to install a new dome? (click to expand)
The process takes around 6+ months. First, submit the application and pay a $595 fee. After about 3 months, Western Power will assess the project and request a $1,320 design fee. Once complete, they'll issue a quote—after payment, the job moves to construction. It’s best to apply early, as the timeline can’t be fast-tracked.
Ready to plan your subdivision?
Send through your survey plan and Western Power drawing (if available). We’ll confirm scope, timelines and a fixed price.